Site Item # under Program on construction: 73
Site name: Construction of drain water treatment facilities, 12 thousand m3 per day (including design-survey works), Krasnopolyansky poselkovy area
Responsible agent under the Program: «SC Olympstroy»
Source of financing: from Federal Budget
Site location: Sochi city, Adlersky district, Krasnopolyansky poselkovy area, on the right bank of Mzymta river, in the district located at 48 km car road Adler— Krasnaya Polyana, the top level area.
Basic technical characteristics:
Output of treatment facilities at design stage shall be 12 thousand m3 per day.
Area of the site for construction of treatment facilities at design stage shall be 2.0 hectare.
Set of facilities:
- Mechanical treatment unit.
- Biological treatment unit.
- Secondary clarifiers.
- Membrane-type filtration unit.
- Disinfection unit for treated drain water.
- Set of units for sediment processing and utilizing.
- Discharge of drain water treated to the Mzymta river.
The final set of facilities will be defined under the Project.
The environmental effect of the Site, range of measures aimed to minimize these effects: In the event of using the mentioned technologies, the treated drain water discharged to the Mzymta river will comply with strictest requirements under current RF Legislation. A through evaluation of the environmental effect will be made in the relevant section under project while period of design documentation preparation.
|